Practical steps to review your skills, protect essential knowledge and prepare your recruitment and training plans for the year ahead.
A new production target, a machine installation or a customer contract can change what your engineering team needs to deliver. The workforce implications are easy to underestimate until a missing skill starts holding up the work.
As Midlands manufacturers prepare for 2027, November is a useful point to step back from individual vacancies and review the wider picture. Do you have the right skills across each shift? Where are you relying on one person? Which capabilities will you need before new equipment or additional work arrives?
A workforce plan does not need to be a complicated document. It needs to connect your business plans with the people, skills, time and budget required to deliver them.
For employers in Wolverhampton, South Staffordshire and the wider Midlands, the following approach provides a practical starting point.
Why Plan Your Engineering Workforce Before January?
Workforce planning is about more than increasing headcount. It can identify where recruitment is necessary, where existing employees could develop, and where better skills coverage would reduce operational vulnerability.
The CIPD describes workforce planning as balancing the skills and people available against an organisation’s future requirements. Its guidance stresses the connection with business goals and the need to review plans as circumstances change. [1]
There is also a regional reason to take the issue seriously. Skills England’s 2026 advanced manufacturing assessment places the West Midlands among the English regions with the highest concentrations of advanced manufacturing employment, exceeding 3% of regional employment using 2024 data. [2]
The same assessment projects around 47,000 additional workers in priority advanced manufacturing occupations between 2025 and 2035, alongside approximately 101,000 workers needing replacement. These are national, long-term planning estimates, not a forecast of Midlands vacancies in 2027. [2]
For an individual employer, the useful question is more immediate: what could prevent your team from delivering next year’s work, and what can you address now?
1. Start with Your 2027 Business Plans
Before deciding which roles to recruit, bring together operations, engineering, finance and whoever manages recruitment or people development.
Review what is confirmed, what is likely and what remains uncertain. A signed contract deserves a different staffing response from a sales opportunity that has not yet been secured.
Discuss the changes that could affect capacity or skills, including:
- New contracts, products or customer quality requirements.
- Additional shifts or changes in production volumes.
- Equipment installations, automation or software changes.
- Planned shutdowns, maintenance work and improvement projects.
- Internal moves, known departures and existing vacancies.
For each change, ask what work must be done, when it begins and who can do it competently.
For example, a new machine may require operator training, programming knowledge and maintenance support. Recruiting another operator will only address part of that requirement.
Keep the assumptions visible. If your staffing decision depends on a contract being awarded by February, record that dependency and the date when you will review it.

2. Map the Skills You Already Have
A headcount report shows how many people you employ. It does not show whether every shift has the capability it needs.
Create a simple skills matrix for business-critical activities. Record who can carry out each task independently, who needs supervision and where there is no reliable cover. Ask managers to validate the entries using observed work, relevant qualifications and any required authorisations.
The example below illustrates the approach. It is not a recommended staffing level or a description of an actual employer.
| Critical activity | Illustrative current coverage | Planning concern | Possible action |
|---|---|---|---|
| CNC setting | One independent setter on the day shift | Limited cover during absence | Develop a second setter and review shift requirements |
| Electrical fault diagnosis | Suitable competence available on one shift | Other shifts depend on call-outs | Assess additional cover and recruitment options |
| Final inspection | Two trained employees | New product needs additional inspection capability | Confirm training and equipment requirements |
| Production supervision | One supervisor with no identified deputy | Limited cover during leave | Develop a deputy through supervised responsibilities |
Include knowledge that may not appear in a job description: a specialist setup, a recurring equipment fault or a customer’s inspection requirements.
Update the matrix when someone demonstrates competence, changes responsibilities or leaves. Attendance on a course alone should not automatically be treated as readiness to work independently.
3. Identify Your Most Important Workforce Risks
Not every gap needs the same response. Prioritise those that could interrupt essential work or take considerable time to resolve.
For each gap, consider the operational impact, existing cover, the time needed to develop or recruit the capability, and when the business will need it.
You may find that protecting maintenance cover deserves attention before adding production capacity. Alternatively, a confirmed project may make a specialist design appointment the immediate priority.
Succession planning also belongs here. The CIPD’s guidance covers business-critical positions as well as leadership roles. [3] In a manufacturing business, that could include a highly experienced technician or setter whose knowledge is difficult to replace.
Use career conversations and confirmed plans to understand potential changes; do not assume someone intends to retire because of their age. Build knowledge-sharing arrangements around the importance of the work and the need for cover.
Our article on the engineering skills gap explores the wider importance of preparing for changes in workforce capability.
4. Decide What to Recruit, Develop or Reorganise
Recruitment is one response to a gap, but it is useful to compare it with other realistic options.
An experienced appointment may be appropriate where specialist capability is needed soon. Internal development may suit an employee with relevant foundations and enough time to learn. Changes to responsibilities or shift coverage may address a problem without creating a new role.
For temporary peaks or clearly defined projects, assess whether appropriately skilled temporary or contract support would fit the work. Consider supervision, continuity and the full cost alongside availability.
Avoid treating apprenticeships as immediate replacements for experienced employees. They need structured development, suitable supervision and a longer planning horizon.
Training also needs protected time. In the IET’s 2025 findings, 50% of engineering employers cited lack of time as a barrier to upskilling or reskilling. [4]
For every development action, specify the skill, the person providing support, the time allowed and how competence will be checked. This makes “we will train someone” a deliverable commitment.
5. Work Backwards from When the Skill Is Needed
The date someone starts is not necessarily the date they can contribute independently.
Your recruitment schedule should allow for approval, search and selection, any notice period, induction and role-specific training. Use your own previous recruitment experience and discussions with candidates to estimate these stages.
Illustrative planning example: Suppose you need an engineer working independently by the beginning of April 2027. If you allow two weeks for approval and briefing, six weeks for search and selection, four weeks for notice and four weeks for induction, the total is 16 weeks. That points to beginning around early December 2026, before allowing any contingency for Christmas availability or delays.
These timings are assumptions, not industry averages or a hiring guarantee. Replace them with realistic estimates for your vacancy.
If the schedule does not fit, make the issue visible early. You may need to bring recruitment forward, adjust the project sequence or arrange suitable interim cover.
For guidance on preparing a clearer local recruitment brief, see our Wolverhampton and South Staffordshire hiring guide.
6. Budget for the Whole Workforce Decision
The advertised salary is only part of a recruitment budget. Build the plan with finance so that the approved figure reflects the actual appointment and its timing.
Include relevant employer employment costs, shift premiums, recruitment costs, induction, equipment, training and supervision. Where a vacancy creates overtime or external cover costs, make those visible too.
For development plans, include the learner’s time and the time of the person supporting them. For a new shift, check whether maintenance, quality and supervisory cover also need to change.
Our West Midlands engineering salary guide provides a starting point for discussing the package. Validate the budget against the specific responsibilities, working pattern and current candidate market when recruiting.
Avoid assuming a standard percentage increase will suit every role in 2027. A specialist appointment, an internal promotion and a trainee position may require different decisions.

7. Include Retention and Knowledge Transfer
A recruitment plan can be undermined if existing employees leave faster than new capability develops.
Use conversations with employees to understand the practical issues affecting their experience: workload, shift arrangements, equipment, management support and progression. Record actions you can deliver and communicate what happens next.
Make knowledge transfer part of normal work. Examples include supervised task rotation, clear setup instructions, documented fault histories and opportunities for a deputy to practise responsibilities.
The IET’s 2025 findings illustrate the challenge: while 80% of employers said they shared knowledge effectively between employees, only 57% reported doing so effectively with retiring staff. [4]
Documentation is a useful starting point, but a procedure is not the same as practical competence. Allow time for another employee to perform the task, ask questions and demonstrate understanding.

8. Keep the Plan Flexible Through 2027
Prepare a base plan for the work you reasonably expect, then consider what would change if demand rose or a major project was delayed.
Agree decision triggers. A confirmed contract, approved machine installation or sustained need for additional shift capacity could prompt a recruitment decision. A delayed project may change the timing of a planned appointment.
Keep a short action register with a named owner, budget, target date and review point. A suggested timetable is below; adapt it to your financial year and operational deadlines.
| Period | Suggested priority | Tangible output |
|---|---|---|
| November 2026 | Review business plans, skills coverage and key dependencies | Agreed priority gaps and planning assumptions |
| December 2026 | Approve budgets and begin time-sensitive recruitment or development | Recruitment briefs, action owners and training schedules |
| January–March 2027 | Deliver appointments, induction and knowledge transfer | Progress against agreed competence and cover requirements |
| Each quarter in 2027 | Compare capacity, costs and delivery needs | Updated decisions and action dates |
Track a small number of measures that help you make decisions: coverage of critical tasks, progress towards competence, vacancy milestones, overtime used for cover and departures from critical roles.
If progress falls behind, review the reason and the operational effect. A completed recruitment action is only useful if it provides the capability the business actually needs.
Frequently Asked Questions
When should manufacturers start planning their 2027 workforce?
Start when business plans begin to take shape. November offers a practical review point, but urgent requirements should be worked back from the date the skill is needed, including recruitment, notice and training time.
Does a small engineering business need a formal workforce plan?
A short plan can be sufficient. Begin with critical activities, current cover, likely changes and actions. Assign an owner and date to each priority so the plan can be used in day-to-day decisions.
Should we recruit experienced engineers or develop existing employees?
Consider the capability required, how soon it is needed and the support available. Some gaps need an experienced appointment; others can be addressed through supervised development. A combination may be appropriate.
How often should we review the plan?
Use a regular review rhythm, such as quarterly, alongside more frequent checks on urgent actions. Revisit the plan when a contract, project, key departure or equipment decision changes your requirements.
Prepare Now for the Team You Need in 2027
The useful outcome of workforce planning is a set of decisions: which skills to protect, which people to develop, which roles to recruit and when to act.
Reviewing those decisions before January gives your business more time to prepare recruitment briefs, organise training and address gaps before they affect delivery.
Based in Codsall, Advanced Resourcing supports engineering and manufacturing recruitment across Wolverhampton, South Staffordshire and the wider West Midlands.
If recruitment forms part of your 2027 plans, explore our engineering recruitment service or contact the team to discuss the roles, skills and timescales your business needs.
Planning your engineering recruitment for 2027?
Tell us which roles and skills your business will need, and when you need them. Speak to Advanced Resourcing about engineering and manufacturing recruitment across the West Midlands.
Sources and Further Reading
1. CIPD — Workforce planning factsheet, 29 July 2025. Supports the definition and connection between business needs, available skills and an adaptable workforce plan. Read the factsheet.
2. Skills England / Department for Work and Pensions — Sector Skills Needs Assessment: Advanced manufacturing, 2026. Published in the June 2026 collection; HTML updated 6 October 2026. Regional employment concentrations use 2024 data. The 2025–2035 projections cover defined priority occupations in advanced manufacturing and are uncertain planning estimates, not 2027 vacancy forecasts. Read the assessment.
3. CIPD — Succession planning factsheet, 5 December 2025. Supports planning for leadership and other business-critical roles. Read the factsheet.
4. Institution of Engineering and Technology — 2025 UK Engineering and Technology Skills Survey. Published 30 September 2025, with the cited statistical summary dated 6 October 2025. These are national employer survey findings, not Midlands-specific 2026 or 2027 statistics. Survey and full report. Statistical summary.
Research checked on 26 October 2026 for planned November publication. The skills matrix, recruitment timings and action timetable are illustrative editorial guidance, not survey findings or guaranteed outcomes.